The deputy of the Save Romania Union, Cătălin Drulă, has sparked strong controversy regarding the construction of the road infrastructure near the capital. According to reports by the media outlet HotNews, the former Minister of Transport claims that the interchange between the A0 and A3 motorways was enlarged far beyond the actual design requirements, leading to an estimated additional public expenditure of 61 million lei and longer travel times for drivers.

The politician points out that the total area of the project increased from the initial 82 hectares to an area of 208 hectares, involving the expropriation of an additional 126 hectares of agricultural land. Drulă compares the dimensions of the infrastructure to the German Frankfurter Kreuz junction, around 30 hectares, noting that the Romanian interchange is seven times larger despite significantly lower traffic estimates, assessed at thirty thousand vehicles per day compared to the three hundred thousand recorded in Frankfurt.

The project also resulted in an overall lengthening of the connecting ramps to 13.7 kilometers, compared to the 7.6 kilometers planned in the original feasibility study. Drulă also points to traffic flow issues, emphasizing that the routes impose longer distances and that the presence of single-lane ramps two and a half kilometers long risks paralyzing traffic in the event of a heavy vehicle breakdown.

The allegations also target the Compania Națională de Administrare a Infrastructurii Rutiere, the road management company headed by Cristian Pistol. According to the parliamentarian, 109 hectares of agricultural land and pastures were allegedly compensated at urban area prices, namely 95 lei per square meter instead of 11, citing among the main beneficiaries a compensation payment of 7.57 million lei to a company linked to the presidency of the Ilfov County Council.